Belgian regulators tell Google to stop datacentre build due to missing permits
Tech Desk
Authorities in Belgium have commanded Google to cease building work on a large datacentre in the southern region of the country. This action follows the US tech firm’s failure to secure approval for requests to modify the original planning permission terms. Wallonia regional official Raphaël Stokis told the public broadcaster RTBF that inspectors visited the site and discovered the building was almost finished with structural work completed, despite the permit being refused.
Advertisement
Mr Stokis confirmed that a verbal order to stop work was issued to the 300 workers on site and this was subsequently confirmed in writing to Google. In a formal statement, the company said it was “committed to maintaining an open and collaborative dialogue” with the regional authorities. A report is being submitted to public prosecutors alleging “a major offence: the illegal construction of a building covering 3 hectares,” according to regional government spokesperson Nicolas Yernaux, who spoke to Agence France-Presse on Friday.
The massive structure occupies roughly 3 hectares of a 50-hectare business park situated on a former coalmine at Aiseau-Presles, located approximately 15km west of Charleroi. It is one of three datacentres originally planned for the site. Earlier this week, the environmental group Greenpeace released a report featuring drone footage which claimed Google was continuing construction work at the location even though it lacked the necessary permits.
Greenpeace stated, “The tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked,” while noting they had filed an emergency appeal with local planning authorities. The group further remarked, “The climate crisis will only intensify in our region. Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed.”
Google’s 2024 permit allowed for the construction of three smaller air-cooled datacentres. However, in 2025, the firm applied to merge two of these into a single, larger facility and proposed a switch to liquid cooling, which would draw 600m3 of water per hour from the nearby Sambre River. Although the regional administration initially approved these amendments in April, the Wallonia infrastructure minister, François Desquesnes, revoked the modified permit in August following appeals from residents and protest groups citing drought concerns.
Advertisement
Google has launched an appeal against that decision to Belgium’s council of state, with a ruling anticipated on 7 January. This legal dispute is the latest facing the company in Europe as major tech firms seek to develop datacentres to support the AI boom. In October, Finland initiated a criminal investigation into potential breaches of environmental laws at a planned Google datacentre in the rural north of the country, where work remains halted pending environmental impact assessments.